New KO drums and 4 pumps installation in Oued zar
Location | Oued Zar |
Year | 2020-2021 |
Client | ENI |
Duration | 1 year |
Project Description | Flare revamping project at Oued Zar : EPC for 2 new KO drums and 4 pumps installation
Project general scope of work : • Detailed engineering of the installation • 2 KO drums fabrication and test at NASR workshop • Procurement of 4 pumps and 2 flame arrestors • Procurement of pumps control panels and electrical material • Procurement of valves and instrumentation material • Installation of the above equipment • Piping fabrication and installation works with relevant supports • Installation precommissioning, commissioning and start up |